The conveyor to remove spoils is in the upper right side.That absolutely is a different tunnel. The Line 2 tunnel is nowhere near that complete at this point in time. Compare pictures from past tbm drives, including TYSSE and Crosstown 1.0 and 2.0.... at this point you would expect to see the conveyor to remove spoils, temporary lighting and unfinished conduit, temporary trackage for the construction material handling.
Once the tbms are extracted, a lot of temporary stuff is removed and the final add-ins begin. We are nowhere near that yet.
- Paul
It looks so small because the tunnel is so big.
There's still a lot of work to go. Those pipes are to supply the TBM.
They'll have to pour a level floor about a third the way up from the bottom.
Here's the Vancouver Broadway SkyTrain tunnel (6m diameter) for comparison:
This was the 10m diameter SkyTrain Evergreen Line tunnel:
Evergreen line with a floor:
and with the dividing wall: