There have been two, potentially important, announcements regarding construction for the Kitchener Line, west of Mount Pleasant recently:
View attachment 539933
And the "METROLINX VENDOR ENGAGEMENT For construction of the Guelph Subdivision Construction Packages 2 and 4 – Kitchener Extension Program" released on Merx.
Can anyone provide accurate info on the scope of these works?
Potential work on the CN portion of the line might include:
- 3rd track from E of Georgetown GO station across the Credit bridge to W of Mount Pleasant GO station
- 3rd track through Brampton station
- additional track from Bramalea GO station to the start of the Metrolinx-owned Weston subdivision
- Rail-rail grade separation W of Heritage Rd and E of Credit bridge
Could Kitchener Extension Package 4 be the island platform and new access tunnel at Georgetown GO station? It was schedule to go to RFI later in 2024 but the design contract was awarded a long time ago.