News   GLOBAL  |  Apr 02, 2020
 11K     0 
News   GLOBAL  |  Apr 01, 2020
 43K     0 
News   GLOBAL  |  Apr 01, 2020
 6.8K     0 
I do think Alstom (pre merger) did a better job building the vehicles than BBD did with the flexitys. So there’s less problem with that plus the line is straightforward.
I disagree.

The first thing I noted on the Ottawa cars on their first day in service was the uneven and sometimes monsterous panel gaps. The second thing I noted was that the flooring had not been bonded evenly to the solid floor underneath. Neither of those things I had noted in any of the Toronto cars that were then being delivered.

Dan
 
Are you sure about that?? It was taking TTC 8-12 days to put a car into service with BBD building them. It was taking 18-24 days for the Alstom order that it is up to 34 days with 4 more to come.
They are longer vehicles to be fair - more to go wrong?
 
They are longer vehicles to be fair - more to go wrong?
TTC are BBD 29m while Finch are 45m by Alstom.

Line 6 and Hurontario cars are the same as Ottawa.

Line 5 and TTC cars are BBD but different models

As to more going wrong with longer cars, Why??

Why are systems moving from 4/5 sections to 7 and 9 sections??
 
TTC are BBD 29m while Finch are 45m by Alstom.

Line 6 and Hurontario cars are the same as Ottawa.

Line 5 and TTC cars are BBD but different models

As to more going wrong with longer cars, Why??

Why are systems moving from 4/5 sections to 7 and 9 sections??
Finch was designed for 60m trains. The use of the 48m trains limits expansion and is a reduction of capacity.
 
No pics but they finally paved the Weston and Finch intersection, the only substantial construction left is the MUP under the CP bridge and the associated paving between Weston and Arrow Rd, no work has progressed here in months from what I saw. I wonder if they will open the line without this work being completed, if not it will delay the line as it looks like it would a few months worth of work.
 
Finch was designed for 60m trains. The use of the 48m trains limits expansion and is a reduction of capacity.
The current platforms (at least at Jane) look to be (using the measuring tool on the City interactive map) to be about 50 metres. With the area protected for a future platform being about 100 metres. Even the station box at Humber College seems to be long enough for a 100-metre platform.

Though I'd think by the time they need trains rather than a single 48-metre car, that they'd be into new equipment anyhow. I don't see a concern here.
 
The current platforms (at least at Jane) look to be (using the measuring tool on the City interactive map) to be about 50 metres. With the area protected for a future platform being about 100 metres. Even the station box at Humber College seems to be long enough for a 100-metre platform.

Though I'd think by the time they need trains rather than a single 48-metre car, that they'd be into new equipment anyhow. I don't see a concern here.
Both line 6 and Hurontario platforms are 50m's long at present time that can be expanded to 100m.

Line 6 will have a harder time adding the phase II for the platform extension than Hurontario that is using the same LRV. Both lines will be seeing work done at nighttime and slow going for the extension being built during the day. Line 6 is full concrete at track level while Hurontario stations are seeing concrete for 2 LRV's including the future station.

The Hurontario platform extensions area for the time being will have shrubs and flowers for the 4 curbs in the centre that will be remove when the platform expansion happens along with the 2 centre curbs. The 2 outside curbs will support the rebar for the new extension with one end remove to allow the connection to the existing platform. We are looking at about 20 years for the expansion has to happen for either line and only once the headway start to get down to 90 seconds.

How much are you loosing going to 45-48m LRV on opening day than a 29m or 2 29m LRV mu?? Going with 45-48m on day one gives you far more capacity than needed and maintain the same headway for at least 10 years on opening day..
 
No pics but they finally paved the Weston and Finch intersection, the only substantial construction left is the MUP under the CP bridge and the associated paving between Weston and Arrow Rd, no work has progressed here in months from what I saw. I wonder if they will open the line without this work being completed, if not it will delay the line as it looks like it would a few months worth of work.
Oh good, I had to flag the raised manholes the other week as I watched a few cars nearly bottom out going over them and had to flag the traffic markings earlier in the summer as they'd completely worn away. Can't wait for the underpass to get going as its really the last major piece of road infrastructure left.
 
If trial running and RSD goes very right for Finch, it very well might open before Eglinton!

I don't want to laugh but I find it a bit funny
Based on the CEOs comments, I would call this almost likely at this point.

He certainly sounded way more optimistic
 
If trial running and RSD goes very right for Finch, it very well might open before Eglinton!

I don't want to laugh but I find it a bit funny
If you look back in the thread for the past year or so, you will see members saying Finch will open before Eglinton. How ML wants to handle this line opening before Line 5 is a behind-the-scenes to the point TTC is forced to delay the opening until Line 5 opens on the same day to a few days later. Don't forget it got to meet Ford schedules for cutting ribbons. 90 days puts the opening in December and 45 days in October.
 

Back
Top