Project Update - May 2025
Construction of the park started again in early May. The park and pavilion are expected to be completed by the end of 2025.
Completion of utility servicing is in progress. Preparation for the hard surface elements of the project, which include walkways, paving stone plazas and asphalt installation for the basketball court area is also underway.
The remaining park scope, which includes the off-leash dog park, natural playground, Northern Lights feature, site furniture, wayfinding signage and extensive soft landscaping is currently in progress. Construction on those elements will begin this summer.
Pavilion construction continued through the winter. The pavilion structure is near completion. The final stage is the interior finishes, which will take place this summer/fall of 2025.
Renewal of 106 Street from Jasper Avenue to 102 Avenue, the remainder of 107 Street from Jasper Avenue and 102 Avenue to the park limits and the perimeter park laneways will begin this summer. 106 Street between Jasper Avenue and 102 Avenue will be closed during construction.