I did some driving from 109 Street west (no pics). I found the following observations:
(1) Almost all of the trenches for LRT tracks have been dug, with many of the underground utilities completed.
(2) More traffic lights at pedestrian crossings, and intersections like 128-129 Street.
(3) Track subbase and base earth have been laid in many parts of 156 Street. Some track forms have been built.
(4) The track mindbender apparatus moves with little bulldozer tracks. It’s currently at the turnoff onto 156 Street South. It looks like both will move north as track construction progresses.
(5) Looks like the concrete between Meadowlark Station and 87 Avenue is largely complete.
(6) 87 Avenue has a lot of roadwork.