I have no idea if it had to do with the LRT work or something else. This area saw no BOT work in the first place.
Some blame for delays and rework falls on Arcadis shoulders as they only got drawing up to 80% so work could start and when they hit 100%, various rework had to be done for various location. Since the designer and the detailing are out of London UK, it could be up to 48 hours to get questions answer due to the time different depending on the question.
Then there ML who has habit of rejecting things if they are off by a mm or two as well dealing with the demands of Alstom to make sure tracks meet their requirements since their LRV's don't meet NA standards and only look at Ottawa LRV's issues since they are the same car for Finch, Hurontario and Hamilton Line.
The City of Mississauga has play a part in delays by not approving permits in a timely fashion even with the fast process in place saying the applications were fill out wrong or lack info with crews standing around doing nothing while waiting for that permit.
The main partner is at fault due to lack of funds to pay for work that has a ripple effect on all other partners as well their subtrades.
Right now, Hydro and the telecommunications companies are holding up work south of the QEW with hydro also delaying work north of the QEW.
MTO has delay some work by weeks and months as they required extra work and other things first before allowing work to happen at the QEW and the 403. The QEW push box work was to happen Thanksgiving weekend that was plan two years in advance only to take place 3 weeks later.
Finger point to one company needs to be pointed to a number of parties. End of the day, the line will open years late like all ML LRT lines and we have to live with it.
Right now, I have no idea what is happening at Topflight and the tracks leading to the OMSF.
I had an unplan look at Maryland Purple Line in June that started in 2017 for an 18 mile line and is to open in 2027 now after the P3 company walked away from the project for various reason and sue the state over it. The project was delay another two years to hire another company on top of all the legal battles that saw stop orders issues and then appeal by various groups trying to cancel the project as well being over budget. The photos I shot of the line over three days can be found in my
Maryland Album and I like the CAF LRV that is 142 feet long. They are getting 28 of them.