Considering it was
Well If I recall, construction started at the same time as Finch, and Finch should be opening this year. So I don’t know why it’s so day behind
If you looked at the corridor at the beginning of the year, there was zero chance opening in 2026 with an 2027 date with a slight chance for the end of 2026..
I haven't looked at the corridor in weeks other than around us and it been dead as a door nail. Different work is taking place on Dundas.
Given no real work has taken place this year as plan, 2027-2028 maybe the opening date subject to a few things now.
Great shots. Should try getting shots of the guideway from Topflight to the OMSF.
The only changes I can see from these shots from my last site visit as follow
407
The ramps have been repaved by the 407 owner and you can see where concrete work was done for the westbound lanes and ramp. Rest of the ramp will be repave by Mobilinx when they finish rebuilding the intersection for the northbound lanes
The ends of the bridge is poured, Looks like 90% of the barrier wall between the guideway and the northbound lanes has been poured. Still have to pour the guideway first before backfilling the ends that will be follow by the curb work for the ramps. Once done, paving of the northbound lanes can take place and traffic relocated to it. Work then can take place to build the guideway from Topflight.
May see concrete pour for the guideway this month.
Topflight
A one of the diamonds is in place with 2 more to go. The two curb tracks have been reinstalled. Still a fair amount of trackwork still to be done with a chance it maybe finish by the end of July. July was to be the completion month with no date for it.
Traffic should be using the intersection come August with a lot of happy drivers.