July 29
My original plan today was a bus ride to Port Credit for a few things, but
@Tim MacDonald posting change that plan. I ended up walking from the Queensway to Port Credit as it allowed me to check a few things on my due list as well do the first walk for that section of the corridor this year. Still have to do Eglington to Derry as I want to check a few things, but may bus ride to those areas,
A small crew has been digging up parts of the guideway base where the OS pole support and cable box for various sections south of Fairview. Southbound curb lane close north of Paisley to the Queensway as hydro ducts are being stalled next to the curb in the road
The base for the Queensway Station has been formed, poured and striped. The southbound guideway base is still not poured. Curb machine sitting at Sherobee and see no work for. With all the traffic lanes moved at the North Service Rd, there is over 200' of guideway that can be built with no interferences with southbound traffic.
The northbound lanes are fully paved from the South service Road to the south side of the QEW west off Ramp. Topcoat in place in the underpass but missing on either side like the rests of the corridor, no concrete curbs in place like is to be like the plans I have seen, and it may have to do that the rest of that intersection still has to be built. All it needs is stripping so it can open, and it may not happen until they rebuilt the south-east corner that is under way. The plan was to have it open in the summer and still 2 months to go.
As Tim as noted and what I have posted in the past, zero work has taken place south of the South Service Road to where Mary Fix Creek starts. Still a lot of sidewalk work to be done as well move a few lights post out of the sidewalk area.
The wooden sound barrier is 100% completed and stained and been that way most of the year. Base for the sidewalk for the fence area as well to Englewood is in place and waiting sidewalk work. Same goes for the guideway. Other than handrail on the retraining wall, Mary Fix Creek is 100% done.
Part of the sidewalk from Englewood to PC station has been poured since I last saw it as well formed for haft of the sidewalk width. The guideway is waiting for concrete base.
Saw only one worker on the upper part of the north section of the station with everything fence off.
The last time I shot the north section of the station was at the end of May and don't recall seeing any changes the first week of July, but the west wall cinder blocks have been installed with no change to the started south end.
The east sidewalk is still close and have built a large U training wall with a deep hoke that I could see and no idea what is going in there. There is a need for a draining area for the sidewalk area as it is flooded after each major rainfall. That area could be for a substation in place of the area on the northside of the rail corridor.
I should note the top of the ramp to Rathburn was being top off last week as well the elevated section retraining wall. I noticed this well pass it last week on the bus.
One reason I started at the Queensway was to see if any work has started on the new hospital and only saw storm drains and waterlines being installed on the west side with two security gates that needs a pass to enter or exit the site at each end with the north one block off.
I just added today shot to my backlog of 1400 shots still to be work on to get me back on track and they will be up in August sometime, but here a few shots untagged