I see why the thread was quite while I was away for June as nothing has change for the corridor before I left or from May.
Took a look of the full corridor today starting at PC to Brampton and leave it to the Brampton folks to fill in more detail what taking place there.
PC hasn't change since early April-May other that the guideway was in place near the end of May. All work is completed for the North Service Rd and area.
Dundas St E Phase 1 work is done with Phase 2 starting with the corner in the same condition. As for the substation area, there was 2 pads when I saw it before leaving, but one pad now with more forming for it as well the edge of the property.
I will have to take a look at the new pathway for the GO station area as well the bridge pier area.
The 403-bridge ramp hasn't been touched at all this month. Looks like more grading may have been place for the wye area.
Topflight: The more I see of this intersection rebuilt, it clearly saying it should have been rip out and done right. The amount of work still to be done to rebuild the rail anchors is still on going and not sure what is plan for the curve section from Hurontario to Topflight. The 2 diamonds are now fully spliced and waiting to be reinstall. The north-westbound curb has been poured including the rebuilding of most of the motel driveway curb along repaving the area. Maybe it will be done Aug-Oct this year, but not July.
OMSF: The area by the 407 terminal is seeing new rail anchoring base rebuilt as well from what I could see, all the way to the OMSF. Will not attempt to say when this work will be completed other than the end of the year at this time.
407-Bridge: The east sidewalk barrier wall in place and waiting railing for it. Forming at each end underway. The guideway is now completed for the rebar work and rail base to allow concrete to be pour for it. Forming underway for the barrier wall between the guideway and the northbound lane at the north end. May see backfilling taking place by the end of July. Will be lucky to see the northbound lanes open by September.
Brampton: looks like more southbound curb has been pour from the 407 to Ray Lawson. No change for the north-west corner. Work has started on the southbound curb in various locations with a pile of storm water pipes waiting to be install. The south-east area south of Steeles looks like it seeing curb work.
As we head into July tomorrow, a good chunk of this year work has failed to take place and pushing opening date closer to 2028 now. It been said that Mississauga mayor expects the line to be in service late 2026 and not a chance in hell unless 7/24 works take place with a number of contractors doing the work not part of Mobilinx team as different track crews. Even then, more like 2027.
I happen to have a look at Sliver City MD Purple Line being built for 16.8 miles and schedule to open in 2027. It had legal issues from the word go that saw one of the judges overseeing the opposing the line case removed from the case as his wife was leading the opposition to the line that would run behind their house. Then the P3 contractor walked away from the project due to conflicts with the government and the contract that was partly built. The remaining work went to several contractors to the point I was seeing not only completed sections, but also the test bed for burning in the new cars. Only saw one CAF 5 section car on the test bed by the complex yard and don't know if anymore inside of the building. By year end, a few more miles of tracks will be ready for testing including the end station that connects to Amtrak, Marc, Metro subway and a large bus hub.
The line is a mixture of centre of the road, one side of the road, next to CSX line with a crash wall between the two systems and next to a path/trail that started the legal issues. Trackwork is meanly RR style with concrete ties block that will see concrete pour over them for various street areas. Stations set back not as far as the Hurontario with better shelters.