Apparently Crosslinx is suing the province for 134M because of Covid. I must confess, I blame the Premier for many things.

I presume this is an attempt to take a bite out of Verster's statement that Yonge station must be completed on the pre-covid schedule or pay penalties.

Vendors considering a bid on Ontario Line and GO Expansion will be watching this pretty closely. I'm guessing in Alliance style tenders that change of law impacting cost will be a risk Metrolinx is forced to absorb.
 
Last edited:
You must have forgotten this:


AoD

These are reasonable claims though. This one will go nowhere. You cant sue for act-of-god situations. Even if you argue that the provinces action because of an act-of-god situation was not adequate, its a very weak argument.

This only shows how desperate they are.
 
These are reasonable claims though. This one will go nowhere. You cant sue for act-of-god situations. Even if you argue that the provinces action because of an act-of-god situation was not adequate, its a very weak argument.

This only shows how desperate they are.
The only valid suing point is how the province handle the pandemic. Being a new thing to all governments, I would say everyone is a newbie and is pretty hard to do the best thing.
Pretty much the only thing ML can be proved wrong is forcing the opening date on them. ML is saying they were already behind and money was given to them to speed up. Now is up to the court to look at the evidence and say is the date reasonable.

This kinda thing also will set the stage for future P3 projects and how much they will bid or the willingness to bid. The risk is clearly too high.
 
viruses don't typically fall under act of god... it's largely for environmental disasters.
I think a lot of contracts invoked the force majeure clause due to COVID--it certainly happened with projects I am involved in, due to inability to travel freely to complete on-site work.
 
I presume this is an attempt to take a bite out of Verster's statement that Yonge station must be completed on the pre-covid schedule or pay penalties.

Vendors considering a bid on Ontario Line and GO Expansion will be watching this pretty closely. I'm guessing in Alliance style tenders that change of law impacting cost will be a risk Metrolinx is forced to absorb.

Last we heard, IO and MX were having a lot of trouble with P3 procurement, particularly around GO Expansion, because the private sector was not willing to take on the level of risk that IO/MX desired to load onto them.
 
I presume this is an attempt to take a bite out of Verster's statement that Yonge station must be completed on the pre-covid schedule or pay penalties.

Well the pre-COVID schedule dictates that the line must be finished by 2021. Putting Yonge aside, do we even consider that a realistic timeline for the rest of the project? End of 2021 is just 14 months away, and several stations are still holes in the ground. I feel like mid-2022 is a more realistic goal at this point (guesstimating here)
 
All large contracts have a claims process where the contractor asks for relief from things that went amiss, invoices for scope changes, and recoups the cost of mitigating extraordinary unforeseens, etc. Normally that happens quietly and even if there are disputes, they get arbitrated in private.
What gets a little silly is when the contract is so rigid and the in service date has such political ramification that the parties have to wrangle these things out in public with little room to compromise.
ML lost a lot of credibility when it took Bombardier to court alleging non-performance on LRT production, when ML’s real objective was to downsize its order. Now we have ML saying it will enforce the Crosstown contract to the letter.
Nobody really expects a project this big to come in on the exact promise date. I have not heard of any single large booboo by the contractor, and the known glitches (eg the discovery work at Yonge-Eglinton) are definitely unforeseens. ML ought to accept some of that risk.
All I can say is, be careful what you ask for. We want the P3 vendors to have good engineering departments, not good legal departments.

- Paul
 
Last edited:
Last we heard, IO and MX were having a lot of trouble with P3 procurement, particularly around GO Expansion, because the private sector was not willing to take on the level of risk that IO/MX desired to load onto them.
ML really doesn't know what they're doing is one of the biggest risk. They keep changing their minds.
All large contracts have a claims process where the contractor asks for relief from things that went amiss, invoices for scope changes, and cost of mitigating extraordinary unforeseens, etc. Normally that happens quietly and even if there are disputes, they get arbitrated in private.
What gets a little silly is when the contract is so rigid and the in service date has such political ramification that the parties have to wrangle these things out in public with little room to compromise.
ML lost a lot of credibility when it took Bombardier to court alleging non-performance on LRT production, when ML’s real objective was to downsize its order. Now we have ML saying it will enforce the Crosstown contract to the letter.
Nobody really expects a project this big to come in on the exact promise date. I have not heard of any single large booboo by the contractor, and the known glitches (eg the discovery work at Yonge-Eglinton) are definitely unforeseens. ML ought to accept some of that risk.
All I can say is, be careful what you ask for. We want the P3 vendors to have good engineering departments, not good legal departments.

- Paul
It's not like they had much to begin with. The Presto mess tells it all.
 