IF we've learned anything from the Crosstown fiasco.....its surely that Metrolinx takes deadlines seriously..... ...
Which is why there is no surprises that the quarterly update to the Capital Project Commercial Pipeline was just published in March....... the last one having been July '24. LOL
Still.... let's see what UT's railroad experts make of it.....
@crs1026 @smallspy and
@reaperexpress
*sigh* If
@smallspy and I ran this railroad.......
The listing makes sense once you realise that "TBD" probably stands for "Too Bloody Difficult". It's hard to fathom how RFP's that were closed a year ago still haven't been awarded. And the number that are marked as "upcoming" often speaks to nothing having happened since prequalification.
A good example is how the listing of work on Kitchener GO line implies slow progress and few shovels in the ground this year
- Heritage Road layover RFP closed last October, not yet awarded
- Guelph Package 2A - Acton passing track - a key prerequisite to counter flow peak service on the GO Kitchener route - RFP not until Q2 this year
- Mount Pleasant GO - preparatory work only towards adding track and the flyover - RFP only projected for Q2 this year
- Guelph Package 3 (ie Mossborough-Hanlon extension of the Breslau passing track) - Prequal date TBD
- Guelph package 4 (likely downtown Kitchener) - RFP not until Q4 2025
- The status of work managed by CN is, of course, not documented
Even simpler packages such as the signalling and layover track at Niagara Falls - Prequal Q2 2025, RFP Q3 2025 - meaning no shovels in the ground this year
Plenty of station renovations (necessary, but not contributing to expansion).
West Toronto Railpath Exension? TBD. Davenport Public Works? TBD
On the plus side, Caledonia station should be mobilising fairly soon. Milton GO 2WAD at least shows some intitial TPAP preparation activity.
In summary, lots of piecemeal bits but little room for confidence that ML is driving to complete anything over this summer's construction season.
- Paul