afransen
Senior Member
They should use the money planned to be spent on the loop to relocate and expand CCTT to Hurontario (either at Rathburn or Burnhamthorpe), and use buses to service the loop with queue jump lanes, etc.
You can't change the design (nor should anyone want to), but if, as the ML apologists on here were trying to convince us a few years ago, they genuinely have learned their lessons, they can employ more competent project managers and contractors, now that Finch and Eglinton have been wrapped up, and Hurontario is not even halfway done. Laying a surface rail line should not take anywhere near this length of time. But it's Metrolinx we're dealing with here, there was never any danger of them learning anything and those who claimed otherwise were merely selling us snake oil.Hurontario started construction basically at the same time as Finch. I don't think there was much opportunity to learn from either Eglinton or Finch.
And what could we even change on Hurontario based on lessons from Finch or Eglinton? The stops are already significantly further apart.
I'm more concerned about the contractor that was hired to construct this line (Mobilinx). If it's true that they're financial underwater, and their credit rating is near "junk" level, then I'm worried the finished product will be of very low quality.Honestly, once you see them ripping up and replacing track in multiple sections of the line, it makes you wonder if we'll even make it to 2030 at this point. There's almost no faith left in the line, and we're seeing the same mistakes that happened with line 5/6 happen with the Hurontario LRT. Imagine just how many more issues they'd have if they built this line elevated, or below grade.
I'm actually concerned that nobody learns anything from past mistakes and we just keep seeing them make the same mistakes instead of learning from them.
Tell them to shift focus to the Kitchener and Milton lines, use the money for all-day service to Mississauga and Brampton. Extend the subway from Kipling to Square One. Done.Unfortunately, nope. Metrolinx would just double down.
If we all thought Finch West and Eglinton were bad, Hurontario is literally the little baby of both of the aforementioned lines. It's already evident that this line is a mess from a construction perspective, and it will be just a bad as a mess operationally.
The thing is, neither Metrolinx nor the Provincial government has learned anything from the failures of Eglinton and Finch West because if they did they would've been rectifying the mess that is Hurontario. But every time we hear news about Hurontario, it just keeps spiralling and gets even worse.You can't change the design (nor should anyone want to), but if, as the ML apologists on here were trying to convince us a few years ago, they genuinely have learned their lessons, they can employ more competent project managers and contractors, now that Finch and Eglinton have been wrapped up, and Hurontario is not even halfway done. Laying a surface rail line should not take anywhere near this length of time. But it's Metrolinx we're dealing with here, there was never any danger of them learning anything and those who claimed otherwise were merely selling us snake oil.
Why do some Mississauga city councilors seem so interested with getting construction started on the downtown loop when the original line appears to be in complete disarray?The thing is, neither Metrolinx nor the Provincial government has learned anything from the failures of Eglinton and Finch West because if they did they would've been rectifying the mess that is Hurontario. But every time we hear news about Hurontario, it just keeps spiralling and gets even worse.
Then we have a clown of a premier who comes out and says that "he loves our public service", but essentially comes out and doubles down that the private sector is doing a much better job at transit construction than the public service could ever do, and he has no intention on scrapping the P3 model.
So let's just sit here and wait for Mobilinx so gradually self-destruct and leave Metrolinx to handle the exploded rubble afterwards. The alarm bells are ringing, but nobody at the province or Metrolinx wants to listen because they are incompetent.
There is something I want clarified, does the loss in credit rating directly apply to the consortium members, or is it just the consortium itself that gets hit with it?Mobilinx has completed only 45% of the track work so far. That part was supposed to be finished by fall 2024. Last year, the P3 consortium’s credit rating was downgraded (again) to BBB-, the lowest rating before it’s considered junk.
The more this project fails, the less bitter I am about the name Doug Ford christened it.
![]()
Large portions of Hurontario LRT track still not laid, intersections unfinished | Globalnews.ca
Construction on the 18-kilometre, 19-stop light rail route between Port Credit and Steeles Avenue began in 2020 and was originally scheduled to be completed in 2024.globalnews.ca
The main players in the consortium are effected as AMICO, BOT and a few others are paid by them and have their risk financially in place.There is something I want clarified, does the loss in credit rating directly apply to the consortium members, or is it just the consortium itself that gets hit with it?
In fairness, this was on you guys. Crosslinx had the same problem - their competing bidder estimated at the time that they were on the hook to lose a billion dollars - and as it turns out, it looks like they were right.The Bid
During the tender process, only two proposals submitted a price. Other consortia pulled the plug right before submission due to the inherent risks of the project delivery method, the client (Metrolinx), and lessons learned from other projects that were already struggling at the time (e.g., Crosslinx). Even after previous governments trimmed the scope and budget, the price submitted was insufficient. Many items weren't priced to Canadian standards, indirect costs were missed, and the small contingency evaporated quickly.
The Bid
During the tender process, only two proposals submitted a price. Other consortia pulled the plug right before submission due to the inherent risks of the project delivery method, the client (Metrolinx), and lessons learned from other projects that were already struggling at the time (e.g., Crosslinx). Even after previous governments trimmed the scope and budget, the price submitted was insufficient. Many items weren't priced to Canadian standards, indirect costs were missed, and the small contingency evaporated quickly.
The Design & Reworks
When COVID hit, designers went home—literally. This added massive hurdles to evolving the design into something constructible. At the OMSF, the traction power substations (TPSS), and the guideway median, the civil work requirements are directly determined by the systems team (Hitachi), who faced their own delivery delays. This forced civil works to proceed at risk, leading to inevitable reworks.
Mistakes in trackwork design at intersections have resulted in the concrete busters you see on-site now. Between design errors and poor supervision, contractors were fired and several people were invited to quit.
The Utility Delay Reality
Standard phasing assumes utility relocation and road widening are finished before the median work starts. This requires coordination with Metrolinx, the Cities of Mississauga and Brampton (both of which are inexperienced with infrastructure mega-projects not managed directly by them), the MTO, and utility providers.
In this case, it failed everywhere. Utilities never moved at the pace they were supposed to due to a lack of commitment and extreme difficulty securing permits from the Cities and MTO—requirements that were unknown during the tender. To keep from stalling, we performed road widening before utilities moved. That’s why you see poles surrounded by asphalt today; it was a desperate mitigation strategy to allow our own utility work (storm, sanitary, watermain) to continue while third parties lagged.
Management & Self-Inflicted Wounds
While "delays by others" are real, we had plenty of self-inflicted wounds. Turnover has been incredibly high, from admin staff up to the Project Director and CEO. In a niche, competitive market, people are constantly being headhunted by mega-projects like the Ontario Line. Bringing in managers with zero Canadian experience sunk the project deeper. Furthermore, internal processes (or the lack thereof) and T&M contracts with partners meant there was often no real incentive for production.
Metrolinx & Accountability
For a long time, dealing with Metrolinx was like talking to a wall. Every call for help regarding permit hurdles or financial stress seemed to fall on deaf ears. However, as of late, there have been key changes in their top management. Since the previous CEO resigned and new leadership took over, the dynamic has shifted. While things seem to be improving, it will take time before these changes have a tangible impact on contractor performance and the final schedule.
As for the possibility of firing Mobilinx, it’s complicated—Webuild is already part of another consortium for the Ontario Line. It’s hard to imagine how Metrolinx could defend that from a PR perspective, not to mention the massive claims and lawsuits that would inevitably follow.
The Schedule
The latest recovery schedule targets a late 2028 completion. Based on the progress I see here and discussions with former colleagues, I don’t believe that is realistic. Between COVID, material shortages, labor strikes, and the factors described above, the timeline is under immense pressure.
I'll keep an eye on the thread and jump in if I can add any helpful context to the ongoing discussion.
I'll keep an eye on the thread and jump in if I can add any helpful context to the ongoing discussion.