Leo_Chan
Senior Member
Just my intuition, but it think they don’t want to show the chaotic and disruptive nature of surface LRT construction.Why doesn't it show the on surface construction east of Science Centre?
Just my intuition, but it think they don’t want to show the chaotic and disruptive nature of surface LRT construction.Why doesn't it show the on surface construction east of Science Centre?
Doug Ford:
Having streetcars downtown isn't a war on cars; adding a tax on advertising vehicles that directly use fossil fuels is.
Even a 1% tax on all internal combustion engine car commercials in Ontario would generate enough revenue to fund some large-scale public transit projects.
Oh, and Doug Ford needs to visit Bangkok one day.
Makes senseJust my intuition, but it think they don’t want to show the chaotic and disruptive nature of surface LRT construction.
Note the delivery spur at the bottom right corner at 0:26 into the video. I like how even if a freight train were to accidentally get switched into it, it would derail at the end buffer rather than enter the EMSF and wreak havoc. Great design!
Not much has really be done on the above grade sections in terms of station construction, so there's really nothing to show at this point. Utility reconstruction/relocation is really what has been taking place so far.Why doesn't it show the on surface construction east of Science Centre?
I honestly thought they would have been further ahead by now. It doesn't even look like they've really started utility relocation between science centre and Kennedy, and there's still huge amounts of work to be done at all stations. With 2 1/2 years left, I have my doubts, hopefully things go according to plan.
I honestly thought they would have been further ahead by now. It doesn't even look like they've really started utility relocation between science centre and Kennedy, and there's still huge amounts of work to be done at all stations. With 2 1/2 years left, I have my doubts, hopefully things go according to plan.
It's not just surface work, some stations haven't seemingly started excavation in areas and concrete pours haven't commenced at many stations.Surface work is ultimately just a road project; I'm not seeing anything concerning in the timeline yet...
The footage used in the video is quite old, dating back to September or so. They had done a reasonable amount of work on the surface sections of the line, and since then they have started putting the final curbs along much of it. They've even dug the trench where the ROW will be built between Pharmacy and Victoria Park.
Dan
It's not just surface work, some stations haven't seemingly started excavation in areas and concrete pours haven't commenced at many stations.
Um excuse me sir, it’s called Eglinton..I wondered about the status of Yonge-Eglinton
...Florin Merauta, chief of railway systems for Metrolinx, said it is a major undertaking involving 47 kilometres of track that will take about three years to complete...
...Eglinton Crosstown crews first started laying track on the $5.3 billion dollar project in August 2017. They went underground with their track work later that year....
...The 19-kilometre corridor will include a 10-kilometre underground portion, between Keele Street and Laird Drive...
...By December 2018, crews are expected to reach the milestone of 10 kilometres of underground track installed. Track will need to be doubled along the entire 19-kilometre corridor to allow for trains to run in both directions....
...By spring 2019, crews will face a new challenge when special track work begins.
Merauta says that’s when crews will move from their straight-line work to installing switches and crossover pieces.
...By late 2020, all 47 kilometres of track is scheduled to be installed and test trains will begin running the route.
The Eglinton Crosstown is scheduled to open in 2021.




