Tuscani01
Senior Member
I wouldn't blame P3 necessarily - this probably a case of taking too much time to sign the contract than actual delays in construction. Frankly, the way the project was procured is kind of a head scratcher - you start building the tunnel without even having the station coming close to being designed, and then go out there and look for a private consortium to do the DBM. The whole thing was dragged out beyond recognition.
AoD
I'm not blaming the P3 process. I actually support the P3 process. This delay will just provide fodder for those who fight the P3 process, especially when infrastructure Ontario has been so proud to announce it was ahead of schedule up until this point.
Which also makes me wonder... where did all of that time go? Moving the TBM over?