Active Member
I think you mean some Transit City projects in general and the Sheppard LRT project specifically were supposed to be delivered in advance of ION. AFAIK Crosstown was always being delivered after ION given how long it would take for the tunnelled section.ION doesn't have the same ATC system, that's one of the reasons it was delayed. Waterloo Region was counting on just using what Crosstown had (which should have had its trains and system in-hand ahead of ION), but the ATC wasn't spec'd yet so Waterloo Region had to go out and source their own. The region unintentionally ended up being the launch customer for the Flexity Freedoms, which is where a lot of ION's delays came from. Not that you'd ever hear Metrolinx / Del Duca fess up to that, they were too busy pointing the finger at Bombardier.