nfitz
Superstar
That only seems to discuss the first stage though, that's to be finished in 2027. While it will be back to three lanes than at Strachan, the next segment and the new ramp to the DVD and the Don Roadway won't finished until 2030. Are they going to accelerate that too, or just shut down for longer.![]()
Province to give Toronto $73 million to speed up Gardiner construction — with one condition
Doug Ford government is giving the city $73 million to speed construction on the Gardiner, on the condition work can be done 24/7.www.thestar.com
so an extra 75 million on a 300 million project mostly to get work done 24/7.
Thats 25% budget increase. At least its coming from the province
Which allows completion a year early
If they really wanted to accelerate they'd start that work now, instead of only doing one section at a time.