Status Update – Lane Closures on 104 Avenue between 105 Street and 121 Street
104 Avenue between 105 Street and 109 Street
● Removal of sidewalks and roadways
▪ North side of 104 Avenue – Complete
▪ South side of 104 Avenue – Commencing on or around August 18
● Underground utility work
▪ North side of 104 Avenue – Complete
▪ South side of 104 Avenue – Commencing on or around August 18
● Installation of soil cells and tree pits
▪ North side of 104 Avenue – Complete
▪ South side of 104 Avenue – Not started
● Installation of permanent streetlights and traffic signals
▪ North side of 104 Avenue – Below ground work complete, above
ground work not started
▪ South side of 104 Avenue – Not started
● Installation of permanent concrete curbs, sidewalks and pavement
▪ North side of 104 Avenue – Complete
▪ South side of 104 Avenue – Not started
● Track slab installation - Not started
104 Avenue between 116 Street and 121 Street
● Removal of sidewalks and roadways
▪ North side of 104 Avenue – Complete
▪ South side of 104 Avenue – Ongoing
● Underground utility work
▪ North side of 104 Avenue – Complete
▪ South side of 104 Avenue – Ongoing
● Installation of soil cells and tree pits
▪ North side of 104 Avenue – Complete
▪ South side of 104 Avenue – Not applicable
● Installation of permanent streetlights and traffic signals
▪ North side of 104 Avenue – Below ground work complete, above
ground work not started
▪ South side of 104 Avenue – Ongoing
● Installation of permanent concrete curbs, sidewalks and pavement
▪ North side of 104 Avenue – Complete
▪ South side of 104 Avenue – Ongoing
● Track slab installation - Ongoing
104 Avenue between 109 Street and 116 Street
● Removal of sidewalks and roadways
▪ North side of 104 Avenue – Complete
▪ South side of 104 Avenue – Ongoing
● Underground utility work
▪ North side of 104 Avenue – Complete
▪ South side of 104 Avenue – Ongoing
● Installation of soil cells and tree pits
▪ North side of 104 Avenue – Complete
▪ South side of 104 Avenue – Ongoing
● Installation of permanent streetlights and traffic signals
▪ North side of 104 Avenue – Below ground work complete, above
ground work not started
▪ South side of 104 Avenue – Ongoing
● Installation of permanent concrete curbs, sidewalks and pavement
▪ North side of 104 Avenue – Complete
▪ South side of 104 Avenue – Ongoing
● Track slab installation - Ongoing