For those who asked about timing here........
We're still not up the to the standard, repeatable and smaller floor plates of the tower.
Once we get there, which we should by October they'll be just ~ 40 floors to go.
We'll be able to assess the time pretty accurately once we see those rise.
At one floor per week, it would would top out (not complete) in summer '26.
At one floor per 10 days it would be top out in late fall '26.
At one floor per two weeks it would be late spring/early summer '27.
From top out, it shouldn't be more than 2 months to close-in the building, and interiors on lower floors will have been underway for some time.
But the time from close-in to early occupancy would probably be in 4 month range, I would think.
All subject to the vagaries of supply chains and strikes.