Interim occupancy was estimated for Mar 2026. Does it look like it will be on time or delayed? Usually 6 months delay on occupancy is quite normal for pre-con.
 
Interim occupancy was estimated for Mar 2026. Does it look like it will be on time or delayed? Usually 6 months delay on occupancy is quite normal for pre-con.

The Townhouses could have Occupancy by March 2026,.... but that's very doubtful for the Condo!

They're using Flying-Table, at about 2 week per floor,... starting 12th-floor now,...6.5 to get to 18 (13-14 weeks) then add a month for mechanical - so top-out mid December, then add 6 month for interior to follow,... and as you can see from my previous photos today, they're just starting on HVAC & piping on ground and 2nd floor,... so I'd say Mid-June 2026 to Start Occupancy for Condo!
 
How many stories are the townhouses? Why does it feel like they are at the same level as the 5th/6th floor of the condo?
 
Last edited: