m5.png
 
December 28th
DJI_0770.JPG
 
April 3
More up on my site

Able to get ground shots now and looks like May/June that it will be at grade
54429705149_5ff2d02dda_b.jpg

54429755023_9627c7a69a_b.jpg

54429506786_a2552580b7_b.jpg
 
So M5 will basically be complete at the same time as M4? Or before?
Off hand, you are looking at M5 been top off about a year from now while M 4 is about 60 weeks from now, That place it about 2 month after M5, depending on the podium of M5 to the point that both are top off about the same time.
 
April 26
As a note, you can see M4 working on the 3rd floor in these shots.
54477805842_2339cb52db_o.jpg

54477805887_299814d818_o.jpg

54477805882_b046fd564b_o.jpg

54478929558_3acfd367f5_o.jpg
 
April 26
As a note, you can see M4 working on the 3rd floor in these shots.
54477805842_2339cb52db_o.jpg

54477805887_299814d818_o.jpg

54477805882_b046fd564b_o.jpg

54478929558_3acfd367f5_o.jpg
Nice, it's almost at grade. As an aside, any thoughts on why M4's been seemingly "stuck" on the third floor for several weeks now?
 
Nice, it's almost at grade. As an aside, any thoughts on why M4's been seemingly "stuck" on the third floor for several weeks now?

These podium floors are huge and complicated. It typically takes 6-8 weeks to do them.

Edit: they are probably 4x the size of the floor plate for the tower.
 

Back
Top