April 1
54425088156_bc3227f0df_b.jpg

54425339738_8715e40aab_b.jpg

54425339698_0bb22a364f_b.jpg

54424236612_fa40d62521_b.jpg
1
 
April 11
More on my site

Blank wall going up on three sides for the second floor with grade being pour
54448099123_c5ccd9b8b6_b.jpg

54448099128_851806331a_b.jpg

54448227370_b1326f7b58_b.jpg

54448099238_ef86848b96_b.jpg

54447861261_e2c381274a_b.jpg

54448099233_be6ff6bae5_b.jpg
 
Hi, looking at current speed of construction and geopolitical situations regarding tariffs, recession etc, what is the time line we are looking at for completion of this building? The current occupancy says Jan/feb2026.
 
Hi, looking at current speed of construction and geopolitical situations regarding tariffs, recession etc, what is the time line we are looking at for completion of this building? The current occupancy says Jan/feb2026.
Those things are unlikely to slow it too much, but that occupancy date is way, way too agressive.

Luckily Centrecourt is generally the fastest builder in the industry as they run 12 hour day construction schedules vs. most builders who do 8 hour shifts, but this is likely looking at a completion in late 2026 at the earliest even considering that. They will be lucky to top out by mid 2026, then will need another 4-6 months to finish up.
 
Those things are unlikely to slow it too much, but that occupancy date is way, way too agressive.

Luckily Centrecourt is generally the fastest builder in the industry as they run 12 hour day construction schedules vs. most builders who do 8 hour shifts, but this is likely looking at a completion in late 2026 at the earliest even considering that. They will be lucky to top out by mid 2026, then will need another 4-6 months to finish up.
Thanks a lot for ur reply, I m a first time buyer in this project, but 50 stories building top out in 12 months? Sounds like inferior quality and rushed construction though.
 
Hi, looking at current speed of construction and geopolitical situations regarding tariffs, recession etc, what is the time line we are looking at for completion of this building? The current occupancy says Jan/feb2026.
Impossible for a January 2026 and more like a 2027 move in date considering this is 50s plus a mechanical roof and they are only at the 3rd floor now. Rule of thumb is a floor a week depending on the weather and time of year. You have 29 weeks left for this year putting the tower at 32 level and to get to the 50th level you are looking at about May 2026 and June for the mechanical roof. You maybe lucky to see move in start by year end of 2026. depending what floor they want to start with first.
 
Last edited:

Back
Top