Feb 6
Part 1
Since this is long I have broken it down into parts
Went to pickup a car today so I could a number of things that allow me to see the south end from Elm to Dundas for the first time this year.
A 3 man crew at Elm doing measuring with one of them with a shovel to clear the snow from the various areas they were measuring and no idea what they were measuring. Trap covering a small area down by the walkway with the rest of the tracks open and not sure what they were doing there.
Tracks are in place now from John St to Hillcrest and no idea what stage they are at. The north-east corner and northbound curb lane being dug up and most likely for duct banks or other connects to the guideway when it gets built there.
The only thing on my radar for the day was to have a look at Topflight after I did what I had to to as well drop a camera of at Nikon for repairs and pickup a new DSLR from Henry's that show up 7 months after I order it. Looks like the other one on order is now discontinued.
The work taking place east of the intersection for Topflight is now completed but no idea why there are patches of concrete that has been cut out not only for the completed sections but also part of the intersection with asphalt in those areas. Some of these patches are on both sides of the new trackwork, About haft of Topflight itself has been removed like I saw in January that was saw cut with most of the new trackwork being installed. There are no left turns into the various driveway including the motel requiring driver to do a U-turn to get to them. Once this area is done, the rest of the road up to the intersection will take place. No idea if the intersection will be rebuilt. The work on the OMSF guideway work from the intersection to where the main area that was completed has seen any work that I saw in December.
A small crew working on the Hurontario guideway north of Topflight intersection to just south of the 407 installing duct banks wit a few 100 feet to go to connect to the intersection..
Northbound trackwork trap at Ambassador that has been missing tracks since 2024.
Sign saying Ambassador intersection close starting February 11 but saw nothing for it going northbound.
Since I still had daylight and time, decided to have a look at the work taking place at Courtneypark Dr To Prologis Blvd. Tracks being adjusted and brace along with formwork to encase the tracks with crews clearing snow from the guideway that will be trap. The sidewalk for the block on the westside has seen a snow pile and the east side was poorly piled Couldn't any real close of the guideway as the snow banks were too high to climb over them as well the area to the sidewalks.
Crews were digging the tracks out south Prologis Blvd that still haven't been poured yet and will be trap off. Lot of snow shoveling to clear those tracks.
Most of the 401 overpass trackwork has been poured with about 25% trap and the other 25% still waiting to be pour. All tracks fully in place,
Since I still had time and daylight I decided to see what I could see at the south end considering it was not on my radar for this month. This would may this posting too long and will break it down in parts.
I did not look at Brampton as I expected noting has change since December and will leave it to the Brampton folks to fill us in if anything has taken place. I may get up there in March.