October 8
Force to do a number of unplanned things today, that I was able to have an unplan look at the corridor starting in Brampton on my way home. Brampton still a dead zone. Hard to say what has taken place for the 407 bridge and ramps. Crew doing grading and landscaping of the creek area from the 407 to the bus driveway.
Crews were working on 2 rail splicing areas for the southbound track. Some formwork for the northbound in/out tracks is in place for concrete pour. Saw no other work and will say October 15 date will be miss with an 23rd opening date.
Saw nothing new for the OMSF guideway but a sump pump sitting there. Could be pouring on the east-west section out of view this week.
Courtneypark Intersection has steel mats in place as well some ties for the northbound track with mats being place for the southbound track.
Fail to note on Oct 4 that all the work between the 401 and Britannia is completed with both lanes open.
Covering has been removed from the northbound track and being use for part of the southbound track at CP. that has been poured.
Mobile sign for southbound traffic place midway between CP and Fairview saying East Fairview close Oct 10-11 between 7am to 7pm and no sign yet for northbound.
Rebar being installed for the Cooksville station.