These are from Jan 2nd, just quick shots from a ZUM bus going into Brampton, apologies for the quality, these give an overview of
two three sections of the line north of the 403, and closer to the 401
First, two shots a few streets north of Eglinton, looks like tracks are coming in, but lots of work needed before getting to final pours and finishes
View attachment 622988View attachment 622989
Second set is by Traders Bank, Some forms for planters and edges are in, light fixtures installed, caterpenary pillars are coming in, but still lots of work needed
View attachment 622990
View attachment 622991
View attachment 622992
Final set, taken over the 401, even less progress here.
View attachment 622993View attachment 622994View attachment 622995View attachment 622996
There is nothing wrong with your photos been shot from a bus at this time of year and are welcome.
Trackwork north of Eglinton has been that way since the summer to the point, various sections of track about 3-5m have been cut out where the ties are embedded in the concrete with the rail laying there. Those sections where rail has be cut must be the areas where the track gauge problems are. Next to no work has been done on the 401 overpass in a year for trackwork
Dec 18
Had to go to Brampton downtown and wasn't expecting to see any work taking place along the corridor and how wrong I was. No less than 4 surveyor crews were checking the guideway with out track to where track was place and waiting to be anchor by concrete or embedded in concrete. I expect work is taking place a night to install the fault formwork for the bridge when the 407 lanes can be partly close for the formwork as I haven't seen anyone working there in the daylight in a long time.
I will leave this to the Brampton folks, but saw material being moved from the 407 area to 2 construction area north of Ray Lawson. What got me was seeing a forklift with a pile of fencing on it north of Ray Lawson and not sure if the crew was removing the fencing or relocating as there was no fencing from that area to the south side of Ray Lawson. No idea what that area look like today.
Dec 20
Crews were placing traps in the guideway from Central Parkway to the CP bridge as well from King to Paisley.
Dec 31
Took a walk to King to get some grocery and saw no change between King and Elm, but the southbound lane from the CP bridge to Dundas have been ready to be open for the last 2 weeks, but still block off.
All my photos up to Nov 30 are now on line and still running a month behind on my Dec photos with a 1,000 still to be done.
It will be interesting next week if work is taking place on the guideway that is currently trap. If there is work, it will be installing duct banks and utilities work, but no idea, it could be this month or next when we hear an update on the line when the public on line meeting happen. I thought going down to Port Credit on Jan 1 to see what has been completed, but never made it ad not a high priory for me these days.