Feb 10
Highlight
Hurontario is now Ine 10 per the Derry Rd Station sign to Port Credit that I shot today. Station still not done.
Four more sets of poles been to be installed to complete the OS poles from the OMSF to the south end of 407 terminal. Some have brackets on them.
Topflight intersection is finally open with no left turn off Topflight. Excavation is underway from Topflight to the section to the south with some underground work taking place as well.
Crossover switches are in place to be spliced in several locations before encased in concrete.
White OS poles being installed north of the 401 that are plain with four by the substation have holes in them on two side with two poles facing e-w and the other two n-s
Most of the track work between the 401 and Britannia has been poured in place or about to.
Crossover at Trader for the switches are in place waiting to be spliced in several locations before encased in concrete.
Long and no photos
My original plan was to do a walking trip up to Eglinton as I wanted to get some urban shots up there as well along the route and take the bus up to Topflight. Seeing some things north of Eglinton, I decided to walk up to Bristol. Since I was close to Matheson, I took a walk up there as well looking at the crossover. Seeing no bus insight, I walked up to Britannia to get the bus.
Northbound traffic using the new lanes that open on Friday south of Brunhamthorpe. Noticed new left turns signals now in place at Elm and Central Parkway. I was wrong about the right turn lane for Burnhamthorpe as there was to be one since the curb was set up for this on day one.
The southbound turning lane for Burnhamthorpe should be open this week as they just pave the area where the bus stop is to be to allow the removal of the road platform. The south-west corner has been paved for the right turn off Burnhamthorpe as well eastbound with barriers around the hydro pole.
They have placed a subbase for the guideway For Robert Speck Guideway since I saw it on Tuesday, A two-man crew were building formwork for the road curb north of the intersection.
On Tuesday, crews were building a dirt subbase at Sq One Dr and gravel has been placed on it. Looking at how the line will cross Sq One, it will require some shifting of the turning lanes while each section is to be built. This will be the next intersection done after Robert Speck is done based on the work in the guideway, I get the impression they plan to build the guideway north from RS to Sq One while RS is being done.
Excavation is completed for the south pier for Rathburn that foundation is in place on both side of that pier for retaining wall support.
When I saw Styrofoam blocks last year for the north 403 pier, I expected they would be used as Geofoam for the ramp to connect the line at the off ramp from the 403 intersection. Those blocks have been moved to the north side in a valley between the 403 on ramp and Hurontario. This will require an extra light or shorter light for southbound traffic to allow trains to cross the southbound road to get to the centre guideway.
Construction is taking place north of the 403 off ramp to Ella Dt to widen the northbound lanes.
Hard to say if the base of concrete to anchor the tracks across the intersection for the two plaza that is schedule to be open Feb 14 as it was cover up, but the topcoat still needs to be poured.
No tracks in place for Eglinton station.
Rails and ties laying in the guideway north of Nahani Way with tracks in place for the southbound track haft way to Trailwood Dr.
Tracks are poured in place from Trailwood to Bristol.
No tracks in place for Bristol station or up to Barondale Dr.
Tracks poured in place from Barondale to Matheson.
Tracks finally in place for Matheson Station and waiting to be spliced and poured in place. The other has haft is poured in place.
With the switches in place at Trader, the missing sections of tracks can be installed.
Britannia Stop still not form or any tracks for that block
Photos to follow