Just got a chance to read the presentation for the update tomorrow. I dont quite understand their tunneling scheduling. Why is it going to take until Feb to finish the last 500m of the western tunnel when it took the same time to bore through 3X the distance? Same for the east. Feb 2018 just to tunnel 1.5km???!! The logic doesnt seem right.....