What's the status on the Light Rail Vehicle Maintenance and Storage Facility at the former Kodak Lands?
As of September, 2014, the first pilot vehicle (Flexity Freedom) for the Crosstown LRT is due for after the
fall of 2015. That's this year. The production of the Flexity Freedom vehicles
was to start in the spring of 2015, with deliveries commencing in the
winter of 2017. The Crosstown LRT was to open by 2020. See
http://www.thecrosst...rogress/funding
While they will not have the ramp problem of the Flexity Outlook streetcars, they do need the space at the factory available to assemble them.
Haven't seen any action at the Kodak lands, other than just the barricading of Keelesdale Drive (northwest corner of Black Creek Drive and Eglinton Avenue West).