An additional Fourth Track early work notice for the LSE corridor was published. This is in addition to the previous notice for the Gerrard to Woodbine fourth track segment that will initially be used to store rail equipment on a siding and the Danforth GO station renovations to accommodate a fourth track.
Birchmount to Kennedy segment (with no mention of replacing the bridge)
Interesting that they would announce this now, because the corridor looks to have just about all the prep work completed to enable laying of the final subgrade and track laying and ballasting. The big impediments are the Birchmount bridge and the Danforth station.
I hope they are not trying to create a separate work zone, ie jersey barriers between the live track and the new one. That would be a hugely inefficient way to lay track.... and a departure from how most railroads do it.
- Paul