As announced last week, the TTC are now putting in the concrete 'base' for the new streetcar tracks on Wellington between Scott & Yonge and, when done, this will complete the rebuilding of the track on Wellington. As they really only started this work yesterday, I suspect it will not be done until later next week.
ROAD RECONSTRUCTION_ SCOTT STREET / WELLINGTON STREET EAST
The City of Toronto will be reconstructing TTC track allowance on Wellington Street East between Scott Street and Yonge Street. To complete this work Scott Street will be closed at north limit of Wellington Street. Right-turns from westbound Wellington Street to northbound Scott Street will be restricted from September 6 to September 19. Through traffic on Scott Street will also be restricted. Road reconstruction will also be taking place at Front Street and Church Street on the south traffic island. Work on the traffic island will take place from September 6th until September 12th