I'll remain skeptical until I see shovels in the ground but here's what the city's website has for the current project timeline. Not sure when it was last updated:
The City is planning a new community recreation centre at the southeast corner of Sorauren Avenue Park, adaptively reusing the existing former Canadian Linseed Oil Mills Ltd. building (1910).
www.toronto.ca
Project Timeline
- Summer 2018: Public meeting to introduce the project
- December 2019: Design team hired
- Summer 2020 to Summer 2023: Community engagement and design development
- Summer 2020 to Summer 2021: Community Engagement Phase A, Towards a Vision
- Fall 2021 to Fall 2022: Community Engagement Phase B, Exploring Design Options
- Spring to Summer 2023: Community Engagement Phase C, Setting the Direction
- 2023 to 2025: Detailed design (current phase)
- 2026: Hire a construction team
- 2026 to 2029: Construction
The timeline is subject to change. Text in bold indicates the current project phase.