I think that there might be a staggered process to them pouring floors that they are technically accomplishing more than a floor a week I have watched pictures of the climbing frame and it very much seems like they pour floors in the same pattern that they did with the transfer slab they do one side one night then they do the middle the next and the far side the next I imagine if you were to look from above when this process is going You would see almost a staircase effect with the slabs