The lobby does look quite inviting!As Construction continues at Empire Phoenix, we’re excited to share all of the newest developments on site. Occupancies have begun and residents are excited to call Phoenix their home. Suite studs and drywall are all 100% complete, kitchen and tile installation is approximately 85% complete, and counter tops are approximately 75% complete. The final paint and appliance installation is 40% and 45% complete respectively, with landscaping at 95% completion. Our beautifully-designed lobby is also 100% complete. As we continue to progress with all other amenities, we are confident they will be completed very soon for all to enjoy.View attachment 415777View attachment 415778View attachment 415779