Bristol station trackwork unfinished from 2025
Barondale is still close and will open this week. The Northbound track at Barondale stills needs to be pour in place from 2025. A section of trackwork for the northbound track stills needs to be rebuilt north of Barondale.
The station ramp itself needs to be pour. There is a section of the northbound track for Matheson station that needs to be pour in place and no idea why it is this way since the southbound is fully poured.
All the trackwork for the crossover at Waltline is ready to be anchor in place with concrete. One thing that has baffle me why is this that from Matheson To Trader that the tracks are above the road and real low from Trader to Burnal
Can See Matheson Station Rail higher than the road at the top of the curb
April 05
Bristol station trackwork unfinished from 2025
Barondale is still close and will open this week. The Northbound track at Barondale stills needs to be pour in place from 2025. A section of trackwork for the northbound track stills needs to be rebuilt north of Barondale.
The station ramp itself needs to be pour. There is a section of the northbound track for Matheson station that needs to be pour in place and no idea why it is this way since the southbound is fully poured.
All the trackwork for the crossover at Waltline is ready to be anchor in place with concrete. One thing that has baffle me why is this that from Matheson To Trader that the tracks are above the road and real low from Trader to Burnal
Can See Matheson Station Rail higher than the road at the top of the curb