A lackluster GO train pic, but they've been doing earthworks at the site for the past 1-2 months and now looks like some drill rigs are at work.

IMG_4551.JPEG
 
Still going through technical resubmissions on the SPA file in pursuit of NOAC. No movement on permits -- all necessary construction permits for Phase 1 (Building C the 31-storey) remain pending. There was a February revision on the issued geothermal permit reducing the number of geothermal boreholes to reflect the first phase of development only (Geothermal Borefield for 2 Tecumseth, consisting of 134 boreholes)
1777668400432.png
 
I wonder if Woodbourne are excited to be paying the rent on the 4 pieces of equipment that have taken up residence on this stalled-at-best...project?
@ProjectEnd Must be some kind of private arrangement where the name is under Woodborune perhaps...TAS has to pay a monthly inflated fee for keeping the equipment at the site
 