I am sure that CN blocks out these tasks on a fairly relaxed basis, the point being they are not going to commit to anything that might collide with their own work programs or unforeseen tasks. So the time buffers in staging and the contingency built in is likely very generous.
It would be hugely inefficient for CN to have dedicated GO expansion crews sitting around waiting for ML to get their stuff together. One hears about cancellations in ML work programs because some moving part isn't ready or someone didn't know what their assignment was. Centrecourt probably fires people (and subs) for such "oops"es.
My comment about the purchase req actually originated with a guy in a CN truck at the work site that we chatted with some time ago - who commented that CN had been expecting and was ready for this task a long time ago, but ML never came through with a signature.
- Paul
It would be hugely inefficient for CN to have dedicated GO expansion crews sitting around waiting for ML to get their stuff together. One hears about cancellations in ML work programs because some moving part isn't ready or someone didn't know what their assignment was. Centrecourt probably fires people (and subs) for such "oops"es.
My comment about the purchase req actually originated with a guy in a CN truck at the work site that we chatted with some time ago - who commented that CN had been expecting and was ready for this task a long time ago, but ML never came through with a signature.
- Paul