Hey everyone!

Based on where T3 is with their current construction, when do you think this tower will be completed? I purchased unit 901.

I would love to hear people's projections.

Thanks again for your feedback.

GTA Inquiry
 
Hey everyone!

Based on where T3 is with their current construction, when do you think this tower will be completed? I purchased unit 901.

I would love to hear people's projections.

Thanks again for your feedback.

GTA Inquiry
Pick a year and month other than 2025 and sit back to see if it happens for move in

As of April 15, 3/4 of the formwork for the 2nd floor is in place with forming missing at the south end where the ramp is to go for the first 5 floors for parking. Going out on a limb, you may see the 5th floor by July and then a floor every 2 weeks for the next 11 floors. After that, it should be a floor weekly for the remaining 34 floors and 1-2 months for the mechanical floors. Weather has a lot to do when things get built as well the workforce building the tower.

You could see topping off fall of 2026 with move in summer of 2027 and no idea how they are planning what floors will see move in first, other than late 2027 or early 2028 for all units. Work will still be on going for finishing touches that will be completed in 2028 at this time.
 
April 25

@Paclo I realized a 2nd crane was installed in March and only realize it today as I drove by considering I shot it in March. Nothing before March for the tower crane.

Looks like this will be a 2027 move in depending how fast they get to the 12th floor Crane one will look after the main tower and that should move faster than the other haft of the 12 story area.

I have to correct myself from my last posting on how much formwork was in place for the 2nd floor as it was it is only a 1/3rd with some forming underway to maybe 50% of the east side. The 2nd crane will deal with the ramp area as well up to the 12th floor only.

Some forming underway to support the 3rd floor at the north end. Did not have time to fully shoot the site today
54476133951_06e8791979_o.jpg

54476133966_b7911d2889_o.jpg

54475291112_64c8ece97d_o.jpg
 
May 22
They are forming the 3rd floor along with building the walls and columns to support it. I is currently taking about 2 weeks to do a floor at this time.

If they maintain the 2 week per floor, the low building roof will be top off by the end of the year. This put the main tower on course to be top off winter of 2027 with a move in for the summer of 2028. It is possible that the small tower owners could move in winter to spring of 2028, but a guess at this time.
 
May 22
They are forming the 3rd floor along with building the walls and columns to support it. I is currently taking about 2 weeks to do a floor at this time.

If they maintain the 2 week per floor, the low building roof will be top off by the end of the year. This put the main tower on course to be top off winter of 2027 with a move in for the summer of 2028. It is possible that the small tower owners could move in winter to spring of 2028, but a guess at this time.
Thanks so much for these updates!

Let's see how things play out.
 
View attachment 665440

Forgot to post this yesterday, but it looks like they’re finally starting the 4th level.
shot it a week ago and they were still form the south 3rd section for the 3rd floor with some work at the north end for the 4th. Slow moving.
 
Aug 15
At the current rate with the 4th floor fully in place now, the 12 story tower will be top off the 2nd week of January 2026 with work taking place for the 13th floor of the main tower. If they do a floor a week, the tower will be in the topping off stage come October 2026 subject to weather.

The earliest I can see owners moving into the 12 story tower will be late summer of 2026 if they are allow to or beginning of summer of 2027 along with the main tower.

They have started the 5th floor walls and columns at the north end.
 