The DP is progressing quickly and there is now an expectation that a building permit application will be submitted by early June pending unforeseen delays. Keep in mind that a DP only needs to pass the advertising period before a partial bp is considered.According to that schedule the DP was submitted in July 2025 with anticipated release in Autumn 2026.
The BP application is scheduled for October 2026 which should permit construction to start in January 2027.
Giddy-yup!!
I would expect to see construction starting this summer, soon after stampede. The taller building will be constructed first.
Edit: I should add that I am working with incomplete information so this is still a prediction. But there are indications this is moving faster than the scheduled construction date of January 2027 shown in previous posts.