  1. C

    Toronto Toronto | Bellwoods House | 45.5m | 13s | Republic | Arcadis

    Looks like completion of this condo is deferred again to at least March 2028 as per this website. More time for Pennies! https://condonow.com/Bellwoods-House-Condos No further progress on permits approval from the city. Only Demolition permit of the car rental business has been issued.
  2. C

    Toronto Toronto | BLVD Q | 43.05m | 10s | Mattamy Homes | TACT

    Foundation and Drains permits were issued.
  3. C

    Toronto Toronto | Q Tower | 197.4m | 59s | Lifetime | Wallman

    Demolition Permit of the parking garage has been issued.
  4. C

    Toronto Toronto | Q Tower | 197.4m | 59s | Lifetime | Wallman

    Looks like various permits have been applied for and are in various stages of approval process. But the City website seems to have just been updated recently since the permit application dates are showing earlier in 2024. Demolition of parking garage seems to be pending also. Shoring permit...
  5. C

    Toronto Toronto | Bellwoods House | 45.5m | 13s | Republic | Arcadis

    It appears that occupancy was pushed from May 2026 to May 2027 based on this website. More time to enjoy Pennies :) https://condonow.com/Bellwoods-House-Condos
  6. C

    Toronto Toronto | BLVD Q | 43.05m | 10s | Mattamy Homes | TACT

    Occupancy has been pushed from Oct 2026 to Jan 2027, based on the updates posted below. https://condonow.com/BLVD-Q-Condos